Friday, 18 October 2013

32. Roof Construction (Part 4)


Roof Tiles Assembly

Once the frame and the trusses has been assembled then we had to follow up with the assemblage of the individual plastic tiles. At first i thought that it would be a piece of cake but it turned out to be one though cookie. The problem occurred due to the fact that most students did not follow the guidelines provided, and they manufactured it based on their own understanding. It caused many problems during the placement of tiles but by intervention of some reliable students (TQ Riley and Friends) they managed to hotchpotch it together. 
View from above
Jigsaw puzzle




Completed

Under the Ridge Downtown...
The Ridge cover was then made by a couple of students that decided to go with a PVC pipe. They cut the pipe by its diameter to produce 2 semi circles and then joint them together to produce a longer ridge. To prevent the ridge from being blown away, some holes were drilled allowing wires to run through them to be tied to the timber ridge underneath. 


Completed Ridge Cover
Finished!
PVC ridge cover




Monday, 21 January 2013

31.Roof Construction (Part 3)



Sarking
As soon as the frames are fixed the next step is to place the sarking on the sloped surface of the trusses. We decided that by using some damp proof course (blue plastic) this item could replicate the functionality of a real sarking which is to prevent rain from penetrating through.               
The plastic was stretched tightly and then stapled from the underside to the existing battens. This is done to prevent sagging of the plastic.



Students cutting the sarking
Completed sarking
















Battens
The battens were placed on top of the plastic to act as a receiving surface for the tiles. (Please take note that the tiles were previously placed on thin plywood). Each batten was spaced approximately to the size of the prepared roof tile.
Completed set of battens


Student placing the first batten




















Thursday, 17 January 2013

30. Roof Construction (Part 2)



The Ridge
Previously the “A” frames was already prepared in advance so to complete the process we used a ridge timber to align all the trusses together. The ridge was screwed on to the A frames and tightened with wires to give extra hold to the overall structure. The 2 corners of the A frame was also reinforced with timber planks to make it more rigid. 

Ridge aligning the trusses
Extra planks at the corner of the trusses














The students then placed the fame on the beams temporarily to get the correct placement and markings to ease the process of drilling and anchoring.

Temporary placement
Markings on the beams












Wednesday, 16 January 2013

29.Roof Construction (Part 1)

Materials for the roof construction

The materials were mainly recycled and we tried as much as possible not to buy new items for the project, keeping it green and real man!
Students were given 10 weeks to collect and make individual roof tiles which are later merged into a complete roof. It’s more or less like a huge jigsaw puzzle that requires some tweaking and adjustment to make everything fit.

The list of materials that was required is as listed below:
1.       Lots of plastic bottles(about 50 each individual)
2.       Single layer plywood(to screw on the bottles)
3.       Various sizes of screws
4.       Concrete anchor(to anchor the A frame to beams)
5.       Plastic or DPM as sarking
6.       Spray , Paint and Industrial coating(for aesthetic and finishing)

Concrete anchor
 

  

                                     

  
Plastic bottle before cut




Plastic bottle after cut and fold





 










             
                                                        






Top side of bottles arranged






Under side of plywood